Temmler Ireland sees the install of a 1.2MW ground mounted system
Temmler Ireland, a pharmaceutical manufacturing facility in County Kerry, partnered with Greenvolt Next Ireland implements a 1.2 MW ground-mounted solar photovoltaic (PV) system. This initiative aligns with Temmler’s commitment to sustainability and reducing its carbon footprint.
The project in numbers
1.2 MW
Installed Power
1,740
Installed solar panels
261 tons
CO2 avoided per year
Project Objectives
- Energy Cost Reduction: Decrease reliance on grid electricity and lower operational energy expenses.
- Carbon Emission Reduction: Contribute to Ireland’s national goal of sourcing 80% of its energy from renewable sources by 2030
- Sustainable Manufacturing: Enhance the company’s environmental credentials by integrating renewable energy into its operations.
Implementation
Greenvolt Next Ireland provided a tailor made, turnkey solution encompassing site assessment, design, permitting, installation, and commissioning. The 1.2 MW system comprises high-efficiency solar panels mounted on ground-based structures optimized for maximum sunlight exposure.
Outcomes
- Annual Energy Production: Approximately 878,736 kWh, supplying a significant portion of Temmler’s energy needs.
- CO₂ Emissions Avoided: An estimated reduction of 261 tonnes annually, contributing to environmental sustainability.
- Operational Savings: Notable decrease in energy costs, enhancing the facility’s economic efficiency.
Results Achieved
The collaboration between Temmler Ireland and Greenvolt Next exemplifies the integration of renewable energy solutions within the pharmaceutical industry. By adopting solar energy, Temmler not only achieves operational cost savings but also contributes to Ireland’s renewable energy targets and environmental conservation efforts.